While monitoring-based commissioning (MBCx) is a relatively new term in the mainstream commissioning dictionary, its practice has been part of some commissioning programs for more than 10 years.
Prior versions of LEED focused on commissioning the dynamic energy-consuming building systems for confirmation of successful implementation of LEED’s sustainability objectives for each project.
Last month, this column explored the best time to functionally test new systems. This month and next month, I want to back up and talk about the best time to prepare the functional performance test procedures (or “scripts” as some people call them).
In the commissioning specification, the owner made the general contractor responsible for the cost of retesting required due to deficiencies discovered during initial functional performance testing.