The demand for reliable power systems in critical facilities continues to increase, putting pressure on engineers to design reliable systems within project budgets that are often decreasing. This article discusses some of the factors to be considered when designing systems for critical facilities and provides examples from a recent hospital design. The case study used throughout this article is for a new hospital that is approximately 1 million square feet in area.

The code requirements for essential power are focused on providing the minimum amount of emergency power to allow people to safely egress a facility. While this amount of emergency power meets the requirements for life safety, it’s often not sufficient for critical facilities that also need to maintain business continuity during an interruption of power. Power systems that cannot be interrupted during utility outages are important to maintaining safe operation of critical facilities and can also support ongoing maintenance activities. When designing normal and essential power systems for a new facility or upgrades to an existing facility, close attention must be given to resiliency, redundancy, and maintainability.

 

Resiliency

Resiliency can be defined as the ability of an electrical system to recover from a disruptive event that can put a stress on the system. The word “resilio” means to leap or spring back. Stress can vary by type and scale and often cannot be anticipated, but when a stress event occurs, the system must adapt and recover within a reasonable time frame based on a facility’s requirements. Some of the common incidents that cause stress to a power system are hurricanes, tornadoes, and flooding, and each of these may interrupt the power grid and disable the utility’s distribution system. Inside buildings, one major concern is flooding of normal and essential electrical distribution equipment, such as normal service switchgear, emergency generators, emergency switchgear, automatic transfer switches, and components of these systems.

Based on previous experience on the impact of buildings from stress events, the following recommendations for the design or upgrade of electrical systems in a critical facility have been developed:

  • Install all major components of the normal and essential power systems above ground level to prevent flooding of the main distribution equipment and the emergency source of power. This includes normal switchgear, emergency generators, paralleling switchgear, automatic transfer switches, and main distribution panels. In addition to the location of the emergency generators, it’s critically important to consider the fuel delivery system, ensure pumps and tanks are located outside of potential flood zones, and that provisions are made to waterproof pumps and tanks to maintain operation in the event of a flood.

  • Install equipment that meets local seismic requirements to be protected from power outages due to damage of electrical system components during an earthquake.

  • Coordinate the installation of mechanical and electrical systems to prevent internal flooding of the electrical distribution system’s main components. For example, a leak in the boiler plant installed on a floor directly above an emergency electrical room may result in electrical system flooding and damage.

When installing electrical equipment above ground level, it’s important to consider the ongoing maintenance of the equipment. Service elevators, removable panels in walls, and designated equipment egress paths ensure that electrical equipment can be moved in and out of the electrical rooms.

Another way to increase electrical system resiliency is to install combined heat and power (CHP) systems. A CHP system, sized to meet the base load demands of the thermal system in the building, will usually produce electrical cost savings. CHP systems cannot be used as standby or emergency power systems, but when combined with on-site emergency generators, a CHP system often allows a facility to maintain some level of business continuity during a prolonged utility outage. True “island mode” may be possible, but it’s important for the facility to have a business continuity plan to ensure critical systems are maintained during one of these outages.

 

New Jersey Hospital - Case Study

The main normal and emergency electrical rooms are located on the third floor of the hospital’s central utility plant, a floor above the major mechanical and plumbing equipment. That location makes the electrical systems more resilient to external hazards, such as natural flooding, and internal hazards, such as leaks in mechanical and plumbing equipment. A detailed egress path was developed for the electrical equipment, including removable panels in the external wall and properly sized freight elevators. This included an analysis of the structural system along the egress path to support the weight of the equipment. The design also includes provisions in the electrical and mechanical systems for a future CHP plant.

 

Redundancy and Reliability

Redundancy of systems is a primary strategy for improving the reliability of both the normal and essential power systems in a critical facility.

The reliability of power systems in a building begins with the utility and reliability of the power grid. For a critical building, it’s advantageous to have the utility provide more than one power feeder with each feeder originating from a separate utility substation. For hospitals, NFPA 99 recommends redundant utility feeds with an automatic transfer scheme between the feeders. This type of configuration provides protection against a failure in one of the utility substations.

Redundancy of normal power systems is often deployed in a “main-tie-main” configuration of the normal service switchgear, where each transformer is sized to carry the full electrical load of the switchgear lineup. The main and tie breakers in the switchgear are also sized to accommodate the full load. This configuration provides redundancy in the event that one of the transformers or incoming feeders fails. It also provides the facility with the ability to perform routine maintenance on the transformers and main breakers without interrupting power to the building.

N+1 redundancy is often employed to improve essential electrical system reliability. The N+1 term is used in a number of other MEP applications, including mechanical, plumbing, and information technology. As applied to the essential system, the letter “N” stands for the minimum required number of emergency generators to support facility operations, and “N+1” represents an additional generator that can allow continuity of operation in case of equipment failure or scheduled maintenance.

In hospitals, critical and life safety branches are required to restore operation within 10 seconds (NEC, 517.32.B). It is not reasonable to assume that multiple generators can start and parallel to a common bus within 10 seconds, so it’s a good engineering design practice to size emergency generators so that one generator is capable of supplying power for all life safety and critical loads. For example, if the life safety and critical load was 1,300 kW, then the base size of generator would be 1,500 kW. The generator plant would include one 1,500-kW generator for life safety and critical loads, one 1,500-kW generator for equipment loads, and one 1,500-kW generator to provide N+1 redundancy. 

Installation of an exterior quick connect for a temporary generator was introduced in the NEC 2017 article 700.3. For instances with only one source of emergency power (i.e. one generator), a quick connect is required to provide emergency power for life safety loads during routine maintenance of the permanent emergency generator. Sizing the quick connect to support not only life safety but also critical branch loads is a good practice. In instances with parallel generators, a quick connect provides additional redundancy and resiliency to the power system but is not a code requirement.

 

Further examples from the case study

All normal substations are designed as “main-tie-main” systems with transformers sized for full normal load. Substation transformers are fed from dedicated circuits connected to different buses of the medium-voltage outdoor utility switchgear that also has a main-tie-main configuration with a closed tie.

The essential electrical system originates at three emergency generators that connect to indoor paralleling switchgear with one provision for a future generator. A temporary generator quick connect is located outside of the central unit plant and is sized to support the life safety and critical loads of the entire campus.

 

Maintainability and Safety

The design of power systems has a significant impact on the ability of the facilities’ staff to perform routine maintenance on the equipment. Staff safety is also of critical importance. There are several strategies that can be employed to improve both the maintainability and safety of power systems.

 

Redundant Normal Feeds to Critical and Life Safety Transfer Switches

In critical facilities, where downtime of electrical systems can significantly impact business operations, the normal feed to automatic transfer switches (ATSs) can be connected to two feeder breakers that are bussed together. In this scenario, one breaker would be closed to supply normal power to the ATSs, and the second breaker would be open. Routine maintenance can be completed on the open breaker, and then it can be closed to momentarily parallel with the other breaker, which will then be opened. The ATSs will not experience an outage and, now, routine maintenance can be performed on the second normal feeder breaker. This configuration allows for seamless operation while providing maintenance flexibility without having to run an emergency generator every time maintenance occurs.

 

Stored Energy Systems for Critical and Life Safety Loads

Stored energy devices, such as uninterruptable power supply (UPS) and flywheel systems, are often used as a short duration power source (up to five minutes) that is sufficient to allow emergency generators to start and transfer loads (usually within 10 seconds). In hospitals, one common application is to install a UPS on the load side of critical transfer switches. This protects those loads from power interruption during short duration outages or regularly scheduled during generator testing.

 

ATS with Bypass Isolation for Critical and Life Safety Loads

It is considered good engineering practice to install ATSs with bypass isolation for critical and life safety power branches. Since the ATS is often a single point of failure in the power system, the ability to maintain those switches is critically important. Transfer switches with bypass isolation allow facilities staff to perform maintenance on the transfer switch by placing it in bypass without interrupting the downstream loads. 

 

Arc Flash Maintenance Mode – ARMS and ZSI

Arc flash is considered one of the most dangerous hazards for maintenance personnel. Arc flash reduction maintenance switches (ARMS) and zone selective interlocking (ZSI) are two of the most common forms of protection when working on energized electrical equipment. ARMS is turned on by staff. Once turned on, all instantaneous settings of protective devices are reduced to clear any fault quickly rather than selectively. ZSI is a communication method between upstream and downstream electronic trip circuit breakers that allows circuit breakers to trip instantaneously on a fault in its zone without sacrificing selective coordination of electrical systems. ZSI is considered to be a more advanced arc flash reduction technology, since it does not require any actions on behalf of the facilities staff compared to ARMS that needs to be turned on and off every time to perform maintenance on energized equipment.

 

Remote Control to Operate Breakers

With advancements in technology for building power distribution systems, major electrical equipment manufacturers have introduced circuit breakers that can be operated by mobile applications that connect to circuit breakers via Bluetooth technology. A benefit of using remote operable circuit breakers is safety of personnel who do not need to be in front of a breaker to operate it.

 

Circuit Breakers with Metering Capability

Electrical distribution systems in critical facilities often must be designed to be adaptable to facility upgrades and program changes. When designing upgrades to an existing power system, accurate trend data about electrical loads is important for the design engineer. Capturing meter data is also useful for troubleshooting when a problem occurs. Electronic trip units on breakers typically have built-in metering capabilities, but without a software system to capture and trend the data, the full benefit of the metering is not being realized. The software solution is often overlooked or removed during value engineering. Manufacturer software for data collection and analysis will show trends in energy usage and provide data for engineers to use to size new equipment and also troubleshoot existing problems in the power system. 

 

Conclusion

When designing power systems for critical facilities, it’s extremely important to consider resiliency, reliability, maintainability, and staff safety. Without proper design considerations for these factors, there is a risk of significant facility downtime, which is often very costly in terms of lost revenue or interruption of business continuity. This article described just a few of the approaches available to improve resiliency, reliability, and maintainability. Design engineers should consider and utilize methods based on project specific requirements and needs.

 

References

  1. NFPA 70 National Electrical Code, 2017
  2. NFPA 99 Health Care Facilities Code, 2018
  3. FEMA P-1019 Emergency Power Systems for Critical Facilities, 2014.

Back To Top