Last month, this column acknowledged the fact that some projects do not have written Owner’s Project Requirements (OPR) documents for the commissioning professional to reference.
Over the past two months, this column has focused on the building owner’s role in obtaining meaningful and timely training on new equipment and systems installed as part of major capital projects. O&M training is one of the most challenging parts of the commissioning process to do well.
The commissioning professional should facilitate at least one design phase meeting with representatives of the O&M trainees, preferably including some future trainees themselves.
I recently commissioned a project that involved replacing eighty 2-pipe, dual-temperature fan-coil units in a nearly 40-year-old high-rise condominium.